What’s on this page:
- How long before I can park on my new driveway?
- How long before my new driveway is usable?
- How does hot weather effect concrete curing?
- If the temperature of the concrete at the time of concrete placement will exceed 77 degrees Fahrenheit, a plan should be developed to negate the effects of high temperatures.
- How long does a concrete driveway take to cure and what is the best method
- If I drive on the slab prior to joints being cut am I more likely to damage it?
Is it really OK to drive on the concrete after only 2 days? My neighbor just had a new driveway installed this week and he came over to my place to ask me this question. I know I should have said to him that the concrete guys that installed it should have told him but no one did so this is my take on the time a concrete drive needs to cure before you should drive on it.
So how long should you wait before driving on a brand new concrete driveway? This will depend on two things thickness of the concrete and the weight of the vehicle being driven on it assuming that the concrete and reinforcement steel is installed correctly. But 48 hrs is not good. ” High Early strength” cement reaches 50% of minimum strength after 7 days ( I think at 70 F about 21 C, longer at lower temperatures). You can check at the Portland Cement Association site. Cement gets stronger for a long ( years) time. Initial compaction ( like vibration) improves the final strength. It is good to keep the surface damp for a couple days after pouring. I would say rebar is necessary for truck traffic mesh is ok if the mesh is design for the extra load.
Even if control joints were cut, the concrete is at a fraction of its ultimate strength (maybe 15-30%, depending on several factors). You run a high risk of breaking it at other locations usually along the edge of the driveway.

Before I answer the question this is the main reason I see concrete slabs failing
One of the biggest mistakes that I have seen in pouring new concrete driveways is that the reinforcement mesh is not lifted into the middle of the concrete. Having the wire at the bottom of the slab is worthless.
They are supposed to pull it up to the middle as they place the concrete. It will not provide any strength at all at the bottom.
If it is at the bottom all over you have a huge problem. Even if the mesh was properly pulled up into the center line of the slab thickness it is really a minimal technique. A good driveway slab installation would also have a grid or re-bar installed into it.
You should search around the edges of the whole slab to see how much more evidence you can find of “mesh at the bottom”. If there is then you need to get the contractor out there to remove this botched job and install the slab properly.
How long before I can park on my new driveway?
Will the slab further strengthen by in the order of 25% over the next 12 hours?
Maybe, but that’s 25% of the current cure extent, which could still be a minor fraction of the ultimate strength. Cure rates depend on many things, from mix to water content to weather to
If you drive over concrete which is still in the early stages of curing/setting and it doesn’t visibly crack, am I weakening the eventual strength of the concrete?
Cracks due to vehicle traffic are usually apparent right away, but it is possible that you’ll crack it and not know it until dirt starts to accumulate on the line or it opens further.
If I drive over concrete which is still in the early stages of curing/setting and it doesn’t visibly crack, am I weakening the eventual strength of the concrete?
If you drive over concrete in the early stages of curing/setting and it doesn’t visibly crack, you are weakening the eventual strength of the concrete.
Cracks due to vehicle traffic are usually apparent right away, but it is possible that you’ll crack it and not know it until dirt starts to accumulate on the line or it opens further. If it doesn’t crack, it’s probably not weakened in any substantial way.

How long before my new driveway is usable?
For the First Two Days – Although your new concrete will become solid fairly quickly, it has little strength and hardness for the first two days. During that time, especially during the first 24 hours, keep all traffic off the concrete. I have written about concrete curing to stop it cracking this is a link to the article on how to cure concrete for extra hardness.
Any damage to the surface of the concrete will be permanent. That means adults, children, and pets, too. Put up warning tape, but once the concreters have left the work site is up to you to keep children and pets off the driveway because they are attracted to your new concrete slab, so be sure to ask your neighbors to keep their children and pets off the fresh concrete. Many concrete projects end up with footprints of children and pets if this is ignored. For the first few hours, this is even more critical. Many homeowners keep a constant eye on their project during this time. Falling leaves, tree sap, and wild animals like squirrels, crows, and other birds can also scar the surface, especially in the first 24 hours.
For the Rest of the First Week – After two days, you can feel free to walk on your new concrete. It’s tough enough at that time to resist scars from walking. However, avoid twisting or skidding shoes on the concrete during that time, and keep bicycles, skateboards, and other toys off the surface. Do not drive on the concrete for the first 7 days. Leave the warning tape in place to let delivery vehicles and others know that they need to stay off your concrete.
After One Week – After 7 days, it’s OK to drive on your new concrete with normal passenger vehicles. Avoid driving near or across the edges of the driveway, though, since those areas are still weaker. Also, avoid skidding things on the driveway or dragging sharp objects on the driveway, since they can still scar the surface.
After 30 Days – When 30 days have passed, your new concrete will have developed almost all the hardness and strength it will have, and you can use it in any normal way. You should avoid allowing heavy trucks, like garbage trucks or moving vans, on your residential driveway. It’s not designed for that kind of load. After 30 days, the curing agent applied to your driveway will have dissipated, so that’s a good time to apply a concrete sealant for the first time. I have been asked about driving an RV on a new concrete driveway so I wrote this piece about it.

How does hot weather effect concrete curing?
Pouring concrete in hot weather could present the following problems:
Hot weather isn’t a general term when talking about pouring aconcrete slab. Hot weather is defined as high ambient temperatures above 90 degrees Fahrenheit, low relative humidity and/or high wind speeds. That’s correct, hot weather isn’t just air temperature. In certain areas, hot weather can be
Increased difficulty when finishing the concrete
The formation of cold joints due to hot weather decreasing the setting time
Reduced strength and durability
Lower compression strength
Additional drying shrinkage of the hardened concrete
Increased risk of cracking

If the temperature of the concrete at the time of concrete placement will exceed 77 degrees Fahrenheit, a plan should be developed to negate the effects of high temperatures.
Have sufficient manpower to manage the concrete when it is being poured and for the finishing process best to have plenty of manpower so that you get the concrete can be installed quickly.
If possible, avoid pouring concrete at noon or during peak times for hot air temperature early in the morning is best before it gets too hot.
When pouring concrete in hot weather, space control joints at smaller intervals than cold weather concrete joints.
Use some sort of windbreak and sunshades to protect the concrete from going hard too quickly.
Plan to haveindoor slabspoured after all walls and roofs are built.
When pouring concrete in hot weather keep a water hose onsite in case temperature gets hotter and water is rapidly evaporating.
Wet the ground that the concrete is being poured onto and wet all the formwork and the tools that are being used to place the concrete
Reduce the mixing time once water has been added to the mix
Implement the correctcuring methodto allow the concrete to set uniformly like keeping the concrete either moist or covered to slow the curing process and make it a lot harder and less absorbent
I know I have deviated from the topic but it is because if you can cure concrete correctly there should little or no cracking and that means a driveway that is stronger and easier to maintain for years to come.

How long does a concrete driveway take to cure and what is the best method
This is the question I am asked a lot and my method is as simple as using a garden hose to wet the surface at least twice a day and if it is very hot I like to cover the concrete after wetting it using plastic or something to keep the surface from drying too quickly.
If I drive on the slab prior to joints being cut am I more likely to damage it?
No, but it is more likely that you’ll end up with crooked (uncontrolled) cracks, which are ugly.
FAQs
How long before I can drive on a new concrete driveway? |? ›
For Concrete: You may drive and park your personal vehicle on your new concrete surface after 7 days. Your new concrete is designed to reach 90% of its full strength potential after 7 days, so feel free to drive your personal vehicle on it then.
How long should concrete driveway cure before driving on it? ›Do not drive on the concrete for the first 7 days. Leave the warning tape in place to let delivery vehicles and others know that they need to stay off your concrete. After One Week – After 7 days, it's OK to drive on your new concrete with normal passenger vehicles.
Can I drive on concrete after 3 days? ›Concrete professionals suggest waiting at least seven days after the crew is finished before parking or driving your personal vehicle(s) on your new concrete. The reason for this is because one week is the time period it takes for your new concrete to achieve 90% of its full potential strength.
How long does it take for a 4 inch concrete driveway to cure? ›Concrete typically takes 24 to 48 hours to dry enough for you to walk or drive on it. However, concrete drying is a continuous and fluid event, and usually reaches its full effective strength after about 28 days.
How long does it take for a new driveway to fully cure? ›Since the liquid asphalt in blacktop needs time to fully harden and cure, usually 6-12 months, your driveway will remain soft and pliable until then. You may walk on your new driveway immediately. You may drive over your driveway after 2 days, but do not park on it for 5 days and possibly longer in hotter temperatures.
What happens if you drive on new concrete too soon? ›You can damage your concrete driveway, both structurally and aesthetically, by driving or walking on it too soon. At a minimum, you may leave tire tracks, footprints, or scuff marks in the surface. At worst, the concrete will crack and its strength will be compromised.
When should I start watering my concrete? ›Many construction specialists recommend watering it down five to ten times per day, for the first week, starting 2-4 hours after it has been poured. The first two to four hours lets the concrete “finish”, which refers to the setting process.
How strong is concrete after 1 week? ›Concrete achieves about 70% of its compressive strength at the age of seven days. After one week from the initial concrete placement and under normal weather conditions, the concrete element can withstand construction loads of labor and machinery used for construction works.
How thick should driveway cement be? ›As for thickness, non-reinforced pavement four inches thick is standard for passenger car driveways. For heavier vehicles, a thickness of five inches is recommended. To eliminate standing water, the driveway should be sloped towards the street a minimum of one percent, or 1/8 inch per foot, for proper drainage.
How long does it take for a concrete driveway to dry? ›In general, concrete is ready for foot traffic within 24 to 48 hours. It is considered partially cured after seven days, which allows for most vehicles, as long as they are not excessively large.
How often should you water a new concrete driveway? ›
If water evaporates too quickly, it will weaken the finished product with stresses and cracking. To put it simply, the goal is to keep the concrete saturated during the first 28 days. The first 7 days after installation you should spray the slab with water 5-10 times per day, or as often as possible.
How long do you have to stay off new concrete? ›Please keep vehicles, children, pets, and yourself off of your newly poured concrete for the next 24 hours. After 24 hours, you can walk on your newly poured concrete, but avoid dragging your feet, 'doing the twist', or allowing your pets to walk on it as their claws can scuff the concrete.
How long does 4 inches of concrete take to harden? ›The general rule of thumb is that concrete takes about 28 days to dry for every inch of slab thickness. Within 24 to 48 hours, the concrete will be ready for foot traffic.
How long does concrete driveway need to cure before rain? ›How Long Should Concrete Dry Before it Rains. If rain is in the forecast for the days or hours after you expect to finish the job, you shouldn't have to worry. As long as the concrete is given 4 to 8 hours after mixing and finishing to set up, rainwater won't affect it nearly as badly as it could.
How long does it take concrete to cure and turn white? ›Although the bulk of the hydration process takes place in the hours and days immediately after the pour, concrete needs 28 days to fully dry. While the slab will harden and lighten in color before 28 days, don't be fooled into thinking it's done hydrating.
Does asphalt cure faster than concrete? ›Compared to concrete, asphalt has a quicker cure time. In most cases, you can drive on your asphalt driveway the same day you install it. With concrete, on the other hand, you'll need to wait about a week before driving on it while it cures.
What happens if concrete gets wet before it cures? ›If the rain continues for several days, water accumulation on a concrete surface can slow down the curing process. As a result, the internal bond between mixture particles will be influenced, and concrete strength will be weaker than the designated strength.
How long should concrete cure before putting weight on it? ›Curing time of concrete is typically 24-48 hours, at which point it's safe for normal foot traffic. After one week, concrete is typically cured enough to handle continued construction including heavy machinery.
How long does it take for 4000 psi concrete to cure? ›Curing should be continued for a period of five days in warm weather of 70 degrees F (21 degrees C) or higher, or seven days in cold weather of 50 degrees F to 70 degrees F (10 degrees C to 20 degrees C). Protect concrete from freezing for at least 48 hours.
Does spraying water on concrete help it cure? ›DO spray new concrete with water. One of the most common methods for curing concrete is to hose it down frequently with water—five to 10 times per day, or as often as you can—for the first seven days. Known as “moist curing,” this allows the moisture in the concrete to evaporate slowly.
Does watering concrete help it cure? ›
Moist curing is a common method of concrete curing. It involves wetting the concrete slab often with water (5-7 times per day) for the first 7 days. This method ensures your concrete slab will be extremely strong and durable, because it allows the moisture to evaporate slowly, preventing cracks and shrinks.
What time of year is best to pour concrete? ›With scorching and freezing weather ruled out for the best possible results, that leaves the spring and fall for optimal concrete pouring. April and May tend to be big months for concrete work, with the temperatures firmly above freezing but not usually climbing into the nineties yet.
What temperature does concrete cure? ›It's advised that concrete be cured at a moderate temperature between 50 °F – 90 °F. In a perfect world, the temperature of fresh concrete should be above 50 °F, but cured and maintained at 50 °F.
What happens if it rains 2 days after pouring concrete? ›Concrete typically needs 24 to 48 hours to dry.
If the rain comes before the 24-hour mark, you may risk your concrete getting damaged. The time it takes to dry depends on the thickness and size of the concrete project you are attempting to take on.
The majority of cracks occur within 2-3 days after concrete has been placed. These are preventive measures which will minimise cracking in that period: See that sub-grade is well-compacted. Check that form work is firm.
Is rebar necessary for concrete driveway? ›Concrete roadways, platforms, and structures typically require some type of reinforcement to help reduce cracking and prevent architectural failure. Most often, rebar (steel bars) are embedded into the concrete before it hardens. However, galvanized panels of welded wire mesh can be used as an alternative to rebar.
How much weight will a 4 inch concrete driveway support? ›Concrete driveways are typically poured four inches thick, giving the concrete driveway enough strength to withstand loads of regular vehicles (up to approximately 8,000lbs).
Is wire mesh necessary in concrete driveway? ›Do All Concrete Projects Need Reinforcement? No, they do not. Larger projects or slabs may need steel reinforcement to provide support or extra strength. Wired mesh can also help resist cracking.
Does rain affect cement curing? ›Rain can weaken the concrete surface and compromise its strength since it can wash off the cement in the mix. This can lead to issues like cracks in the concrete and delays in the curing process, both of which can lead to a poorly finished surface.
Is it better for concrete to be too wet or dry? ›When a concrete mixture is too wet, it causes a greater amount of shrinkage during the drying process than is needed. As a result, the concrete has a great likelihood of cracking and for those cracks are likely to be a fairly good size.
Is there a difference between concrete and cement? ›
What is the difference between cement and concrete? Although the terms cement and concrete often are used interchangeably, cement is actually an ingredient of concrete. Concrete is a mixture of aggregates and paste. The aggregates are sand and gravel or crushed stone; the paste is water and portland cement.
Can you put too much water on new concrete? ›Having too much water in your concrete will reduce the strength of the cured slab, increasing the risk of shrinkage and cracking. Cracked concrete is particularly problematic in a climate where you can expect freezing and thawing conditions, as the slab will not be as durable.
Should you spray water on a new driveway? ›Your new asphalt driveway will soften and harden as temperatures rise and fall. Watering down your driveway with a hose on hot days will temporarily harden the asphalt. This is helpful, but not mandatory.
Will water damage new concrete? ›Rain on freshly finished concrete can damage the surface, and in extreme cases, wash the surface off the concrete exposing the aggregate. To prevent this, covering the concrete with hessian will protect the surface from running water, reducing the risk of erosion.
Can you pour new concrete over concrete? ›Yes, you can pour fresh concrete over existing concrete. As long as your concrete is in mint condition, this task is doable. If you decide to pour a new mixture over an old slab, be sure it is at least 2 inches thick.
Does concrete take 100 years to fully cure? ›Does concrete take 100 years to cure? No, this is a bit of a myth with the concrete industry. While concrete does continue to harden indefinitely, pore moisture has to drop below a certain level at some point and this isn't typically 100 years.
What makes concrete harden faster? ›Add calcium chloride. Including this compound into the wet concrete mix before pouring is an easy way to quicken the concrete solidification time – this compound accelerates the process of cement hydration.
Does thicker concrete take longer to cure? ›Thickness of the concrete slab - Thicker slabs will take longer to dry obviously. However, this is not linear; a 4 inch thick slab will not cure 4 times slower than a 1 inch thick slab, although that is the current rule of thumb.
How long does 5 inches of concrete take to cure? ›Curing times for concrete
Technically, concrete never stops curing. In fact, concrete gets stronger and stronger as time goes on. But, as far as we're concerned, to reach a practical strength, most industrial concrete mixes have a 28 day curing period.
Once the concrete has been finished (between 4-8 hours after pouring) and has set hard enough for walking on, the effects of rain should be minimal. The curing process is a chemical reaction, with ready mix concrete taking up to 28 days to fully cure.
What might happen if heavy rain falls 5 hours after concrete is poured? ›
You would be left with a weakened surface and the possibility of related problems in the future. They might include dusting of the surface, an unsealed surface that will allow far more water to be absorbed, and a reduced ability of the slab to resist cracking due to freeze-thaw cycles.
Do I need to cover fresh concrete if it rains? ›If rain is forecast on the day you are pouring concrete, make sure the site is well covered with plastic sheets and tarpaulin to keep the ground as dry as possible. If it starts to rain during the pour, make sure you are prepared with plastic sheets and timber to construct a shelter over the fresh concrete.
How can I speed up my concrete curing? ›Using warm water
As an essential ingredient in any concrete mix, water plays an important role in the curing process and can affect curing times in a number of ways. For example, if you use slightly warmer water in your concrete mix, you can encourage a quicker reaction and, in turn, a quicker curing time.
Usually this white or off-white discoloration to concrete and masonry forms when soluble salts and other water dispersible materials come to the surface through capillary voids as a result of temperature changes, moist migration, condensation, rain, dew, and/or too much water in the mix.
How thick should a concrete driveway be? ›As for thickness, non-reinforced pavement four inches thick is standard for passenger car driveways. For heavier vehicles, a thickness of five inches is recommended. To eliminate standing water, the driveway should be sloped towards the street a minimum of one percent, or 1/8 inch per foot, for proper drainage.
What type of driveway lasts the longest? ›Concrete, cobblestone, asphalt, brick, and interlocking pavers are the most durable driveway installation options available today. Apart from their lengthy lifespans, these materials also hold up well in any climate, require minimal maintenance, offer a smooth drive, and elevate your home's first impression.
Is it cheaper to use asphalt or concrete? ›1. Cost Differences Between Asphalt and Concrete Driveways. The cost of an asphalt driveway is typically cheaper than concrete, costing $2.00 to $4.00 per square foot. Asphalt prices tend to fluctuate in comparison with crude oil prices.
How can I make concrete cure faster? ›- Weather is a factor. If your concrete is exposed to the elements, you won't be surprised to learn that the concrete will dry faster in warmer, sunnier conditions. ...
- Using a heater. ...
- Using warm water. ...
- Reducing the amount of water. ...
- Avoid hard trowelling.
As for thickness, non-reinforced pavement four inches thick is standard for passenger car driveways. For heavier vehicles, a thickness of five inches is recommended. To eliminate standing water, the driveway should be sloped towards the street a minimum of one percent, or 1/8 inch per foot, for proper drainage.
How long does 4 inches of concrete take to dry? ›The general rule of thumb is that concrete takes about 28 days to dry for every inch of slab thickness. Within 24 to 48 hours, the concrete will be ready for foot traffic.
How often should I water new concrete? ›
If water evaporates too quickly, it will weaken the finished product with stresses and cracking. To put it simply, the goal is to keep the concrete saturated during the first 28 days. The first 7 days after installation you should spray the slab with water 5-10 times per day, or as often as possible.
What happens if you don't water new concrete? ›Concrete that is not moist-cured at all dries too rapidly, and reaches less than half its potential design strength. It will also have a greater number of shrinkage cracks.
Does higher PSI concrete crack less? ›Concrete strength is measured in pounds per square inch (PSI). The higher the PSI the more durable your concrete will be and will thus be resilient to cracking.
Is too much water bad for curing concrete? ›Having too much water in your concrete will reduce the strength of the cured slab, increasing the risk of shrinkage and cracking. Cracked concrete is particularly problematic in a climate where you can expect freezing and thawing conditions, as the slab will not be as durable.
What is the best PSI for a concrete driveway? ›The typical concrete strength used for a driveway is in the 3000 psi to 4000 psi range, although temperate areas of the country may use lower strengths. Contractors, when ordering ready mixed concrete, should advise the producer of the intended use for the concrete.
What slows concrete curing? ›2) Use retarding admixtures
You can slow your set time by adding retarders to the concrete. Retarders slow the set time to allow concrete to receive an appropriate amount of time to complete the chemical reaction and maintain a higher slump.
High temperatures mean faster curing, but fast curing equates to weaker strength in the end.
What temp does concrete cure best? ›Upon pouring and throughout curing, the concrete must be kept at 40 degrees if more than 72 inches thick, 45 degrees if 36 to 72 inches thick, 50 degrees if 12 to 36 inches thick, or 55 degrees if less than 12 inches.
Is gravel necessary under concrete? ›Whether you pour concrete for a walkway or patio, a strong gravel base is required to prevent the concrete from cracking and shifting. Gravel is especially important in clay soil because it doesn't drain well, which results in water pooling under the concrete slab and slowly eroding the soil as it finally drains.
Do you need gravel under concrete driveway? ›Because concrete is a very porous material, it will absorb any moisture that it contacts. This can cause pooling. Without crushed stone, pooling water will settle under it and erode your slab. Adding a layer of crushed stone will add proper drainage, as well as create a barrier between your slab and the ground.